| Network Rail are adding two additional through platforms at Waverley and simplifying the track layout, and this collection will contain shots of work as it progresses. Additional preparatory work for the Airdrie - Bathgate - Edinburgh electrification is also taking place |
101: Looking south from Platform 1 showing the platform end and the use of the former stabling siding location for a materials store Buy Print |
102: Looking north from Platform 1 with the Calton Road exit in the background - the platform takes shape but the track is still to come Buy Print |
103: Framework of the old pedestrian access to Waverley Steps remains as new overbridge steelwork is installed Buy Print |
104: Steelwork on the north side of platform 1/19 which looks as if it will support stairs Buy Print |
105: The old bridge framework disappears Buy Print |
106: New diamond crossing and LED signals - note the sleeper across the track Buy Print |
107: Twin walkways now in place Buy Print |
108: Little activity in the web of scaffolding Buy Print |
109: New blends seamlessly with old Buy Print |
110: 170411 observes progress Buy Print |
111: Point clamped out of use Buy Print |
112: 170451 awaits departure from platform 1, with plant parked on the old post office area off Calton Road. Work appears untidy in this area Buy Print |
113: DR73913 sits in the loop Buy Print |
114: Stone cleaning continues Buy Print |
115: Loop appears finished at the east end - the notice is a bit redundant since the platform finishes there anyway! Buy Print |
116: The temporary access road area looks much tidier! Buy Print |
117: New steps viewed through a gap in the temporary fencing Buy Print |
118: View from the temporary steps showing the replacements Buy Print |
119: Bridge decking progresses Buy Print |
120: On track plant in South Loop Siding Buy Print |
121: Wagon and Komatsu bulldozer Buy Print |
122:Komatsu bulldozer with rail wheels Buy Print |
123: View looking east on South Loop Siding Buy Print |
124: Road-rail crane with attached match wagons Buy Print |
125: Sleeper indicating the point at which track removal stops Buy Print |
126: Materials storage - note the new hoardings bloacking the access to platform 20 Buy Print |
127: South Loop siding is no more, but evidence of reballasting on waht will be the new platform road Buy Print |
128: More ballast for distribution Buy Print |
129: Interesting parking scenario Buy Print |
130: On track plant now stabled at the east end of the South Loop Siding Buy Print |
131: Looks like a rethink required here - the signal post is a new installation! Buy Print |
132: Balmoral platform west end ramp Buy Print |
133: Balmoral Platform still has a way to go Buy Print |
134: south loop siding gets a buffer Buy Print |
135: top and tail road railers Buy Print |
136: lift shaft progresses Buy Print |
![]() |
![]() |
![]() |
|
© 1998-2009 - All copyrights rest with the Author [ descript.ion | Buy Prints of this Collection | Index ] |